Caledonian Maritime Assets Limited (CMAL), Scotland’s publicly-owned ferry company, has formally accepted the delivery of MV Loch Indaal from the Cemre yard in Turkey. This is the second of four ferries being built at the yard for the nationalised operator. The first, MV Isle of Islay, was handed over earlier this year. MV Loch Indaal is now heading for Scotland – just twenty months behind schedule…
The ferry was originally due to be handed over in February 2025. The original bill for all four Turkish ferries came to £200 million. In September 2026, ministers quietly signed off another £20 million to get the last three finished. This followed CMAL’s unusual decision in June 2026 to take ownership of three unfinished ferries while under construction. Kevin Hobbs, CEO of CMAL, said:
“Taking ownership of the vessels at this stage is a precautionary move to reduce risk, protect the investment already made, and support our objective of bringing these vessels into service as quickly and efficiently as possible.”
The Loch Indaal’s two sisters, Lochmor and Claymore, are still sitting in Turkey, due for delivery in the first half of 2027. After the Glen Sannox saga dragged on for years, Holyrood’s idea of a good ferry is one that turns up within two years of the date on the contract…
Peter Hitchens isn’t a fan of Grand Theft Auto VI:
“Once we have filled our skulls with this sort of liquid manure, we have lost a vital part of our souls. I was perfectly serious when I suggested a church visit. This electronic poison undermines 2,000 years of Christian civilisation.”